The Utah Department of Transportation (UDOT) will be conducting a Chip Seal Roadway project in Box Elder County on SR-38, between SR-13 and SR-30. This project will begin on July 18th and run through August 20th. 


Construction crews will be in the area Monday through Friday between 7 a.m. and 7 p.m.

The Utah Department of Transportation (UDOT) will be conducting a Chip Seal Roadway project in Box Elder County on SR-38, between SR-13 and SR-30. The project will address activities such as:

• soft repair
• chip seal
• flush and rumble strip work
• guardrail removal and replacement
• tree removal
• striping
• sign removal and installation
• seeding

 

PLEASE NOTE:
-Speed Limit Reduction-
35 MPH Flaggers, pilot cars, & directional signage will assist

-Temporary Lane Closures-
Temporary lane closure and delays, northbound, at Mile Post (MP) 2, during tree removal.

-Guardrail Removal & Replacement-
Guardrail removal and replacement near MP 16 requiring lane shifts. MP 14 and MP 5 guardrails will be raised.


Beginning Monday, August 1, construction crews will begin chip sealing on the far north end of the project and work south bound. We are aiming to complete a total of 8 lane miles of chip seal per day. This will put us on track to finish the total 38 lane miles of chipping in 5 days.

Flaggers and pilot cars will be in place to help navigate traffic, with only minor delays.  